Full Kitchen Renovation — Open Concept Layout
Project Budget
$45,000
– $65,000 CAD
Project Description
Required Skills
Property Type
House
Permit Status
Required
Material Preferences
Prefer solid wood cabinetry (not MDF), quartz countertops (not granite), matte black hardware, 3x12 subway tile in white. Open to contractor recommendations on flooring species.
Milestone Progress
Manage →Demolition & Structural Work
Due 2026-03-25
$12,000
Approved & ReleasedRough-in (Electrical & Plumbing)
Due 2026-04-05
$9,500
Submitted for ApprovalDrywall, Insulation & Painting
Due 2026-04-18
$8,000
In ProgressCabinetry & Countertop Installation
Due 2026-04-30
$18,500
PendingFlooring, Fixtures & Final Touches
Due 2026-05-10
$7,000
PendingQuotes (7)
Submit QuoteMarcus Beaumont
$55,000
8 weeks
Elena Pasternak
$52,000
10 weeks
Derek Fontaine
$61,000
7 weeks
Harjit Brar
$48,500
11 weeks
Activity Log
Project posted by Sandra K.
Feb 18, 2026
Quote received from Elena Pasternak — $52,000
Feb 19, 2026
Quote received from Derek Fontaine — $61,000
Feb 20, 2026
Quote received from Marcus Beaumont — $55,000
Feb 21, 2026
Quote received from Harjit Brar — $48,500
Feb 23, 2026
Elena Pasternak shortlisted by client
Feb 25, 2026
Quote from Marcus Beaumont accepted — Project now In Progress
Mar 01, 2026
Escrow funded: $55,000 CAD
Mar 02, 2026
Project start — Demolition commenced by Beaumont Renovations
Mar 15, 2026
Milestone 1 (Demolition & Structural) marked complete by Marcus B.
Mar 25, 2026
Milestone 1 approved by Sandra K. — $12,000 released
Mar 26, 2026
Assigned Contractor
Marcus Beaumont
Beaumont Renovations Inc.